Capex & the cost of downtime

What does the renovation cost while income is interrupted?

Overview · What & why

A decision, before a calculation.

Renovation cost includes the work and the economic consequences of doing it. Vacating space, phasing around tenants and restoring services affect income and schedule. A cheaper construction plan may take longer, reducing receipts or increasing interest. Consider each consequence once in the appropriate cash-flow period.

A concrete example

80,000 SF at $10 annual rent and 75% occupancy generates $50K monthly base rent. Four months of full interruption represents $200K foregone rent relative to continuing that income, before any expense savings or financing costs.

What to remember

The renovation calendar belongs in the investment model.

Before using this in a project: Tenant relocation terms, work sequencing, affected area, interim operating costs and lender conditions.