EBG Studios · Development Atlas · DRAFT — For review & feedback
The primary case study
Juniper Ridge Data Center.
A fictional 20-acre site becomes a 12 MW enterprise data center, owned and operated by one company. Follow the people, evidence and commitments that connect an open field to occupied data halls.
From land to live capacity
One campus. The whole development story.
The site must connect to power and fiber. The building must manage heat and support operations. The enterprise must justify capital and lifecycle costs against its business service needs. Those are connected questions.
Two schematic data halls, electrical and cooling yards, a service entrance and a retained landscape buffer. The enterprise also owns its IT equipment: an additional $48M initial teaching allowance. No reliability tier or engineering certification is implied.
Before there is a building, there is a business need. Maya works with the chief information officer and application owners to plan a twelve-megawatt enterprise data center. One company will own the campus and use it for its own applications, data and private cloud. The first decision is whether the workload forecast and resilience needs justify investigating a dedicated facility.
Eli checks access, neighboring uses, fiber routes and possible electrical service. A nearby power line does not prove that usable capacity will be delivered when needed. Noor works with the utility on capacity, connection scope and timing while the team compares site alternatives and community impacts.
Surveyors mark boundaries while investigators examine soils, water, environmental conditions and title. The sponsor seeks site control with investigation rights and clear deadlines. A difficult finding can change the design, the price or the decision to proceed. The land remains unbuilt while this evidence is assembled.
A concept rises from the field. Morgan, the project architect, brings the data halls, staff spaces, safe circulation and building envelope into one coordinated design. Eli shapes the site and drainage. Noor plans power and cooling around the enterprise workloads. Together, they make room for maintenance, security and future change, test resilience against business needs, and prepare drawings that reviewers and builders can understand.
In Norfolk, Nebraska, Maya and Morgan meet city planners, building reviewers, the fire marshal and the public works team. Eli coordinates drainage and utility connections. State environmental reviewers assess stormwater coverage and any permits triggered by the equipment. Each reviewer protects a different public interest. The team records decisions and conditions, because land-use support, a building permit and permission to occupy are separate milestones.
The capital committee reviews the business case: one hundred forty million dollars for the facility, plus forty-eight million for enterprise IT equipment in this teaching example. Sam aligns the approved funding, construction sequence and long-lead orders. The enterprise also funds operations, equipment refresh and the migration plan. A finished shell alone cannot deliver the business service.
The authorized site work begins. Excavators grade the platform, crews install below-ground services, and the team controls runoff and protects the retained buffer. Foundations start to trace the future data halls. Early work is inspected before later construction covers it.
Alex leads the commissioning team through equipment tests and integrated systems testing. Facilities operators rehearse alarms, transitions and recovery procedures before enterprise workloads depend on the building. Unresolved failures remain on the issues register. Regulatory permissions, facilities acceptance and IT service readiness are separate gates that must align.
The enterprise campus is working. Facilities technicians maintain the infrastructure while IT teams operate the applications. Jo reviews service availability, security, actual load, energy and total operating cost. Capacity planning, equipment refresh and recovery exercises continue throughout the building’s life. Success means dependable service for the business, supported by evidence and a funded operating plan.
Capacity serves the business. Ownership has a lifecycle cost.
Juniper Ridge is owned and operated by one enterprise for its applications, data and private cloud. The capital committee evaluates business need, resilience and total cost of ownership. All figures below are fictional teaching assumptions.
Allocation reserves capacity for application teams. Actual measured load, installed IT capacity and planned allocation are different measures. Unallocated capacity is not a certified resilience reserve.
Ten operating years, constant annual IT load and PUE, initial capital at time zero and year-end operating payments. Operating costs escalate at 3.0% annually; the year-six refresh is an explicit nominal amount. Present cost discounts cash outflows at 8.0%. The baseline $140M facility budget comprises $4M land, $8M site works, $102M construction and systems, $10M soft costs and $16M contingency. Initial IT is $48M; facilities operations $4.2M/year and IT operations $2.4M/year exclude the separately calculated electricity.
Excludes financing structure, tax, depreciation, residual value, decommissioning, software licensing, network carrier charges, migration cost and business benefits. Scope these for an actual capital decision. Allocation alone does not reduce the fixed capital or operating budget.
Riverton Logistics Center is fictional. Its site, figures and complications are educational assumptions. Your committed decisions build a traceable alternative to the baseline.
Riverton Logistics Center
An 8-acre opportunity. A 100,000-SF ambition.
Demand is a hypothesis. Utilities are uncertain. Loading matters to the tenant. Follow each decision and see how cost, time and value develop together.
Modeled propagation: chosen site changes land/utilities; revised diligence adds a $200K provisional allowance; Concept B changes cost, area and assumed owner income burden; approval and construction decisions change cost and delay. Both concepts preserve your chosen area; only B applies the saving and income penalty. Other decisions remain narrative evidence. Committing delays enables calculated carry, so the comparison also changes the carry convention. Stage 9 actuals are a separate performance review.
Riverton begins with a hypothesis: local distribution businesses need flexible loading and modern clear heights. The sponsor has $5M of equity and prefers a single-phase project. These are fictional investor criteria, not universal standards.
Riverton compares an 8-acre served site, a cheaper peripheral parcel and an infill parcel with uncertain approvals. The cheapest parcel needs a utility extension; its cost belongs in the site budget.
An environmental memo flags historic fill, the utility letter promises only a future capacity review, and a survey shows access crossing an adjoining parcel. Riverton must resolve these uncertainties before waiving contingencies.
A $400K construction saving reduces assumed annual NOI by $60K. At a 6% cap rate, that is $1M less value. The cheaper option leaves $600K less value above cost. The NOI effect is an explicit hypothetical user-utility assumption.
Riverton receives a drainage condition and a possible six-month delay. Its financing requires a minimum 1.20× DSCR and a new review if timing changes. These illustrative conditions vary by lender and jurisdiction.
Riverton needs a $180K loading revision. Critical equipment is four months late; expediting costs $120K and recovers two months. The remaining contingency must cover both known changes and future uncertainty.
The Riverton shell is finished, but a fire-system test is pending and the occupancy document is missing. Paint touch-ups do not carry the same readiness consequence as these blockers.
Riverton reaches 88% occupancy at $9.75/SF, while nonrecoverable expenses rise to $65K. Learners distinguish revenue and expense causes of the NOI gap before choosing an operating response.
Change the context
Supporting projects. Shared principles.
Fictional learning case
Harbor Yard Acquisition
Fictional leased industrial acquisition. The $9M land/purchase input is the purchase price; $200K soft costs cover closing. Existing leases begin at 92% occupancy. Annual net rent grows at the selected rate. Permanent acquisition debt starts at closing; construction timing does not apply.
Test this: Can collections, expiring leases and capital needs support the purchase basis?
Fictional learning case
Foundry Works Renewal
Fictional 80,000-SF industrial value-add. $5.5M purchase, $1.6M renovation, 12 months without rent, then 90% occupancy. Detailed mode treats the bridge facility as interest-only until same-balance permanent takeout. Interim income and cash-out refinancing are not assumed.
Test this: Does the income improvement justify renovation, downtime and the bridge takeout risk?
Fictional learning case
Cedar Court Homes
Fictional 24-home infill development. 24,000 rentable SF at $24/SF/year is equivalent to $2,000/month per 1,000-SF home. Expenses include owner operating costs; no separate rent recoveries.
Test this: How do owner-paid expenses and the ratio of rentable to gross area change the housing economics?
Supporting project files
Different assets ask different questions.
Harbor Yard · acquisition rent roll and underwriting file
A fictional 90,000-SF existing industrial property offered at $9M, with $200K closing costs and a $100K funded reserve. Three leases cover 82,800 SF. All three initially pay $11/SF/year net base rent; 7,200 SF is vacant. The aggregate model starts at 92% occupancy and $75K of annual owner expenses.
Fictional lease evidence · supplied for analysis, not a market survey
Tenant
Area
Annual net base rent
Remaining term assumption
Harbor Textiles
40,000 SF
$440,000
2 years
Parcel Loop
30,000 SF
$330,000
4 years
Local Parts Cooperative
12,800 SF
$140,800
5 years
Vacant
7,200 SF
$0
Unleased
Investment tension: the largest tenant supplies about 48% of occupied base rent and has the earliest expiry. Before extending its current income through the hold, review renewal intent, competing premises, tenant credit, concession obligations and required fit-out. The integrated preset aggregates annual NOI growth; it does not automatically roll each lease on these dates.
Decision artifact: reconcile the $910,800 initial rental revenue to leases and collections, test vacancy at the first expiry, and compare sale proceeds after costs and payoff. The acquisition begins at closing without a construction delay.
A fictional 80,000-SF older industrial building costs $5.5M. Before work, assume half the area is occupied at $8/SF/year. The modeled intervention requires a full 12-month closure, so the integrated development period receives no interim rent. After reopening, the target is $12 net rent and 90% occupancy; $80K of annual owner expenses leaves a target NOI of $784K.
Illustrative $1.6M renovation scope
Package
Allowance
Evidence required
Roof and envelope
$450,000
Condition survey and watertightness specification
Lighting and controls
$200,000
Performance and commissioning criteria
Loading and circulation
$550,000
Tenant requirements and access review
Office and service areas
$400,000
Scoped layouts and comparable bids
Investment tension: the initial $320K occupied annual rent is foregone during closure, but it must not be deducted again from a forecast that already has zero receipts. The purchase, $200K site work, $450K soft costs, $250K contingency and financing also need funding. The bridge and permanent takeout must be evaluated even if the target rent is achieved.
Decision artifact: compare a slower lease-up with the target, test permanent takeout against bridge payoff, and explain how much value comes from NOI improvement versus a different exit cap. The separate transition mini-lab illustrates average occupancy along the path.
A fictional infill housing project contains 24 homes averaging 1,000 rentable SF. The $24/SF/year rent assumption is equivalent to $2,000 monthly per home. At 95% occupancy, annual rent is $547,200; $160K of owner operating expenses leaves $387,200 NOI. These are assumptions, not an affordability claim or a market quotation.
Program and delivery questions
Topic
Assumption or question
Decision owner
Area
24,000 rentable SF; gross area and circulation need design reconciliation
Architect
Operating burden
Owner-paid services and maintenance are included in the $160K aggregate expense assumption
Property manager
Access and approvals
Verify emergency access, drainage, parking and applicable local approval requirements
Civil engineer and local authority
Lease-up
Target 95% occupancy; test slower leasing and owner expense increases
Leasing and asset management
Investment tension: gross building area may exceed rentable area, while owner-paid operating costs are significant relative to rental income. Copying a warehouse’s rent convention or operating-cost ratio would distort the housing case.
Decision artifact: reconcile the unit and SF program, test a rent and expense downside, and compare total cost with stabilized value at the assumed 5.5% cap. Do not interpret that assumed cap as a current market fact.