Each lead brings the answer together with the people named below. Maya represents the developer and enterprise owner; specialists and public reviewers retain their own responsibilities.
? Key questions to answer
How should the campus and building fit together?
Arrange data halls, staff spaces, secure circulation, service yards, accessibility and expansion around the site and enterprise brief.
MPrimary responsibilityMorgan · Project architect
With: Eli (site & civil engineer); Noor (power & cooling engineer); Jo (operations lead).
Does the concept meet the need at an acceptable cost?
Test usable IT capacity, resilience, capital cost, operating cost and delivery time together rather than optimizing only building area.
MPrimary responsibilityMaya · Development lead
With: Morgan (project architect); Noor (power & cooling engineer); Sam (construction manager); Jo (operations lead).
Corporate finance evaluates the business case.
↳ Key problems to solve
Building, civil and equipment plans competing for the same space
Resolve equipment clearances, drainage, structure, access routes and maintenance space while the concept is still inexpensive to change.
MPrimary responsibilityMorgan · Project architect
With: Eli (site & civil engineer); Noor (power & cooling engineer); Sam (construction manager).
A feasible-looking plan built on optimistic assumptions
Test power delays, cost escalation, workload growth and operating costs; adjust the scope or phase the investment when the plan lacks headroom.
MPrimary responsibilityMaya · Development lead
With: Noor (power & cooling engineer); Sam (construction manager); Jo (operations lead).
→
What this milestone needs to produce
A coordinated concept, tested cost and schedule, and a feasibility decision with explicit assumptions.
Feasibility brings the physical plan and economic plan together. Buildable area, circulation, parking and user needs shape the rentable program. That program drives cost and income, which determine whether value supports the required investment. Treat each design as a hypothesis: a smaller cost number may hide weaker tenant utility, lower rent or less useful space.
The decision map
Information becomes a commitment.
Bring the evidence
Site constraints and user program
Concept designs and cost estimates
Rent, occupancy and valuation assumptions
→
Ask the right questions
What fits after setbacks, access and drainage requirements?
How does the configuration serve intended users?
What is the total cost, including soft costs and carry?
Does the project still work under less favorable assumptions?
Proceed · revise · pause
→
Pass the work forward
Comparable concept options
Development pro forma and sensitivity
Preferred concept with a reasoned investment test
People & information
Who needs to be in the conversation?
01
Architect
Translates user requirements into a workable concept.
Shares evidence with the development lead and the other stage disciplines.02
Estimator
Prices scope, quantities and uncertainty.
Shares evidence with the development lead and the other stage disciplines.03
Developer & investor
Compare cost, value and risk together.
Shares evidence with the development lead and the other stage disciplines.
Reveal overlapping workstreams and information handoffs
Parallel work, shared decisions
Projects move forward together.
Illustrative relative activity, not a duration schedule. A stage can loop back as evidence changes. Select another discipline to see where it contributes.
Apply the same development principles to Riverton Logistics Center. This supporting case uses its own warehouse assumptions and preserves your recorded logistics decisions.
Decision studio · Stage 04
Can a cheaper building be worth less?
Hands-on
You are the project’s development lead. Change cost savings, area and tenant-income effects; compare both concepts. Use the fictional evidence below, make a choice and explain what you would verify.
Open the project file · 2 documents
Concept A
100,000 rentable SF. $13.5M total development cost. $900K stabilized NOI.
Concept B
Simplified configuration saves $400K. Hypothetical loading compromise reduces annual NOI by $60K.
Illustrative configuration only · no engineering inference
Same area and cap rate; different cost and tenant utility
Metric
Concept A
Concept B
Total cost
$13,500,000
$13,100,000
NOI
$900,000
$840,000
Implied value
$15,000,000
$14,000,000
Value above cost
$1,500,000
$900,000
What your choices mean
The revised configuration changes value above cost by -$600,000. A $60,000 recurring NOI reduction lowers value by $1,000,000, while saving $400,000 in cost. This is a hypothetical tenant-income effect; geometry does not automatically determine rent.
Judgment exercises accept supported alternatives. Diagnostics need 80% to complete. Saved decisions feed the continuing case; practice reset preserves its last committed decision.